A close cooperation in planning and quality assurance minimized loss of time due to quality deficiencies. The processes of so-called 'requirement management' stretch from review to management of sub-suppliers, and installation.rnOur experiences of bringing in new sub-suppliers into the market show varying results. Due to their differing experience and professionalism, some exceeded our expectations, but the opposite also happened. One of the major sub-suppliers failed in both quality and documentation early in the project. The responsible main contractor did not respond in the way that was required and expected.
机译:计划和质量保证方面的紧密合作将由于质量缺陷而造成的时间损失最小化。所谓的“需求管理”过程从子供应商的审查到管理一直到安装。我们将新的子供应商引入市场的经验显示出不同的结果。由于他们的经验和专业水平不同,有些超出了我们的期望,但相反的情况也发生了。在项目初期,主要的子供应商之一在质量和文档方面都失败了。负责的总承包商没有按照要求和预期的方式回应。

著录项

  • 来源
    《Nuclear Engineering International》 |2009年第665期|p.30-31|共2页
  • 作者

  • 作者单位
  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

  • 入库时间 2022-08-18 00:49:49

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号