首页> 外文期刊>Nuclear future >Remediation of the FGMSP at Sellafield: the first transfer of bulk sludge
【24h】

Remediation of the FGMSP at Sellafield: the first transfer of bulk sludge

机译:塞拉菲尔德的FGMSP修复:第一次污泥转移

获取原文
获取原文并翻译 | 示例
       

摘要

1. This paper looks at the first-generation magnox storage pond (FGMSP) sludge retrievals programme, considered one of the most important high hazard reductions at Sellafield. 2. There were many challenges around the retrieval of more than 1,500 cubic metres of radioactive sludge, lying at the bottom of the 160-metre-long storage pond and within the wet bays. 3. The project had a major emphasis on reducing project risk by routinely asking: 'Can this be achieved in a more cost effective and safer manner?' This resulted in a total of 86 project innovations being raised. 4. Key lessons include the positive impact of applying a decommissioning mind-set to deploy simple, innovative solutions, and utilising historically-proven techniques in order to achieve safe and timely delivery of key solutions for future decommissioning.
机译:1.本文着眼于第一代玛瑙存储池塘(FGMSP)污泥回收计划,该计划被认为是Sellafield最重要的高风险减少措施之一。 2.在160米长的储水池底部和湿湾内,要回收1500立方米以上的放射性污泥面临着许多挑战。 3.该项目主要通过降低常规风险来降低项目风险:“能否以更具成本效益和更安全的方式实现这一目标?”这导致总共提出了86个项目创新。 4.关键教训包括采用退役思维方式部署简单,创新的解决方案,以及使用经过历史验证的技术以实现安全,及时地交付关键解决方案以供将来退役的积极影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号