Risk allocation in a public-private partnership: a case study of construction and operation of kindergartens in Kazakhstan

机译:公私伙伴关系中的风险分配:哈萨克斯坦幼儿园建设和运营的案例研究

获取原文
获取原文并翻译 | 示例
       

摘要

In Kazakhstan, a transitional nation in Central Asia, the development of public-private partnerships (PPPs) is at its early stage and increasingly of strategic importance. This case study investigates risk allocation in an ongoing project: the construction and operation of 11 kindergartens in the city of Karaganda in the concession form for 14 years. Drawing on a conceptual framework of effective risk allocation, the study identifies principal PPP risks, provides a critical assessment of how and in what way each partner bears a certain risk, highlights the reasons underpinning risk allocation decisions and delineates the lessons learned. The findings show that the government has effectively transferred most risks to the private sector partner, whilst both partners share the demand risk of childcare services and the project default risk. The strong elements of risk allocation include clear assignment of parties' responsibilities, streamlined financing schemes and incentives to complete the main project phases on time. However, risk allocation has missed an opportunity to create incentives for service quality improvements and take advantage of economies of scale. The most controversial element of risk allocation, as the study finds, is a revenue stream that an operator is supposed to receive from the provision of services unrelated to childcare, as neither partner is able to mitigate this revenue risk. The article concludes that in the kindergartens' PPP, the government has achieved almost complete transfer of risks to the private sector partner. However, the costs of transfer are extensive government financial outlays that seriously compromise the PPP value for money.
机译:在中亚转型国家哈萨克斯坦,公私伙伴关系(PPPs)的发展处于早期阶段,并且具有越来越重要的战略意义。本案例研究调查了一个正在进行的项目中的风险分配:以优惠形式在卡拉干达市建造和运营11所幼儿园,为期14年。该研究利用有效风险分配的概念框架,确定了主要的PPP风险,对每个合作伙伴承担某种风险的方式和方式进行了重要评估,强调了支持风险分配决策的原因并总结了经验教训。调查结果表明,政府已将大部分风险转移给了私营部门的合作伙伴,而这两个合作伙伴共同承担了托儿服务的需求风险和项目违约风险。风险分配的重要内容包括明确分配各方责任,简化融资计划以及鼓励按时完成主要项目阶段的激励措施。但是,风险分配错过了为改善服务质量和利用规模经济创造动力的机会。研究发现,风险分配中最具争议的要素是运营商应该从与儿童保育无关的服务中获得的收入流,因为双方都无法减轻这种收入风险。文章的结论是,在幼儿园的PPP中,政府已将风险几乎完全转移给了私营部门的合作伙伴。但是,转移成本是政府的大量财政支出,严重损害了PPP的物有所值。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号