Schedule Delay Leading Indicators in Precast Concrete Construction Projects: Qualitative Comparative Analysis of Korean Cases

机译:预测混凝土建设项目中的延迟领先指标:韩国病例的定性比较分析

获取原文
获取原文并翻译 | 示例
           

摘要

This paper analyzed 19 precast concrete (PC) construction project cases from Korea using fuzzy-set qualitative comparative analysis to explore the relationship between the conditions of PC projects, observable at an early stage of the projects, and actual schedule delays. The following combinations of PC project conditions leading to schedule delays were identified: (1) the use of multiple types of PC components and nonuse of building information modeling (BIM) for schedule management; (2) PC construction included in the critical path, insufficient experience of the contractor in PC projects, and nonuse of BIM for schedule management; and (3) nonresidential building project, insufficient experience of the contractor in PC projects, and non-use of BIM for schedule management. To understand these findings more deeply, this research further investigated the relationships of the use of BIM with other schedule delay factors based on focus groups. The PC project schedule delay leading indicators identified in this research can help construction managers to mitigate schedule delay risks at an early stage in PC projects.
机译:本文分析了韩国的预制混凝土(PC)建设项目案例使用模糊定性的比较分析,探讨了PC项目条件之间的关系,在项目的早期阶段观察,以及实际的进度延误。确定了导致安排延迟的PC项目条件的组合:(1)使用多种类型的PC组件和非建筑信息建模(BIM)进行时间表管理; (2)PC结构包括在关键路径中,PC项目中承包商的经验不足,并非用于安排管理的BIM; (3)非尼斯建设项目,PC项目中承包商的经验不足,并非使用BIM计划管理。要更深入地理解这些发现,本研究进一步调查了基于焦点小组的其他时间表延迟因素使用BIM的关系。本研究中确定的PC项目进度延迟领先指标可以帮助建设管理人员在PC项目的早期阶段减轻时间表延迟风险。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号