The sandstone mass rock in front of spillway bucket of a 60-m high dam constructed in the early 1960s experienced serious erosion in view of the continuous scouring action of flowing water. The erosion of rock mass, which was about 3-10m deep, posed serious threat to the safety of the dam. It was therefore proposed to construct a 1.5-m thick reinforced concrete raft immediately downstream of the spillway bucket and tie the same to the bed rock using 10-m long passive anchors. However, in view of the 10-m deep pool of standing water, it was found essential to construct an underwater coffer dam using preplaced aggregate concrete (colcrete). The paper describes the salient features of the construction of coffer dam, raft and passive anchors.
机译:1960年代初建造的60米高的大坝溢洪道桶前的砂岩块岩由于流水不断冲刷作用而遭受了严重侵蚀。大约3-10m深的岩体侵蚀对大坝的安全构成了严重威胁。因此,有人建议在溢洪道铲斗的下游立即建造一个1.5 m厚的钢筋混凝土筏,并使用10 m长的被动锚将其绑在基岩上。但是,考虑到10米深的积水,人们发现必须使用预先放置的骨料混凝土(混凝土)来建造水下围堰。本文介绍了围堰,筏板和被动锚构筑的显着特征。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号