Equipment Failure Survey Quantifies Outage Impacts

机译:设备故障调查量化了停电影响

获取原文
获取原文并翻译 | 示例
           

摘要

This survey shows that postponing repairs and replacements can have significant cost and schedule impacts if the result is a forced outage. Cost increases can be more than 1,000% of the cost of a planned outage, and schedule impacts can be as much as 800%. Staffing limitations and equipment lead times accounted for 80% of the schedule impacts. In at least 35% of reported failure events, owners identified no deteriorated condition or warning signs of failure. These results suggest that regular condition monitoring and reliability centered maintenance programs could prevent failures, but it may not be possible or practical for condition monitoring to prevent all forced outages. Component age may be a better indicator of failure as the survey results demonstrated that often there was not a condition based indicator that preceded the forced failure. Planning investment decisions (including investment in strategic spare parts for replacement to limit outage times based on age, available condition assessments, and engineering judgment are critical to effectively managing your hydropower fleet.
机译:该调查表明,如果结果是强制中断,则推迟维修和更换可能会产生重大成本和进度影响。成本增加可能超过计划中断的成本的1000%,而进度影响可能高达800%。人员限制和设备交付时间占计划影响的80%。在至少35%的报告故障事件中,所有者没有发现状况恶化或故障预警迹象。这些结果表明,定期进行状态监视和以可靠性为中心的维护程序可以防止发生故障,但是状态监视以防止所有强制停机可能是不可能的或不切实际的。组件年龄可能是故障的更好指标,因为调查结果表明,在强制故障之前通常没有基于状况的指标。计划投资决策(包括对战略备件的投资以根据年龄限制更换停运时间,可用的状态评估和工程判断)对于有效管理水电车队至关重要。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号