Field test of the long-term settlement for the post-grouted pile in the deep-thick soft soil

机译:深厚柔软土壤中灌浆桩长期沉降的现场试验

获取原文
获取原文并翻译 | 示例
           

摘要

The long-term settlement characteristics for the cast-in-place bored pile in the deep-thick soft soil are investigated by post-grouting field tests. Six cast-in-place bored engineering piles and three cast-in-place bored test piles are installed to study the long-term settlement characteristics. Three post-grouting methods (i.e., post-tip-grouting, post-side-grouting, and tip and side post-grouting) are designed and carried out by field tests. Results of the local test show that decreased settlements for the post-side-grouted pile, the post-tip-grouted pile and the tip and side post-grouted pile are 22.2%similar to 25.8%, 30.10%similar to 35.98% and 32.40%similar to 35.50%, respectively, compared with non-grouted piles. The side friction resistance for non-grouted piles, post-side-grouted pile, post-tip-grouted pile and the tip and side post-grouted pile undertakes 89.6 similar to 91.3%, 94.6%, 92.4%similar to 93.0%, 95.7% of the total loading, respectively. At last, the parameters back analysis method and numerical calculation are adopted to predict the long-term settlement characteristics of the cast-in-place bored pile in the deep-thick soft soil. Determined Bulk modulus (K) and a creep parameter (K-s) are used for the back analysis of the long-term settlement of the post-grouted pile. The settlement difference between the back analysis and the measurement data is about 1.11%-7.41%. Long-term settlement of the post-grouted piles are predicted by the back analysis method, and the predicted results show that the settlement of the post-grouted pile are less than 6 mm and will be stable in 30 days.
机译:通过后灌浆场测试研究了深厚软土中展开钻孔桩的长期沉降特性。安装了六个钻孔钻孔工程桩和三个流钻钻孔测试桩,以研究长期沉降特性。三种后灌浆方法(即,尖端灌浆,后侧灌浆和尖端和侧面灌浆)由现场测试设计和进行。局部试验结果表明,侧侧灌浆桩的沉降减少,尖端灌浆桩和尖端和侧面灌浆桩的沉淀量与25.8%相似的22.2%,类似于35.98%和32.40与非灌浆桩相比,分别与35.50%相似。非灌浆桩的侧面摩擦阻力,后侧灌浆桩,尖端灌浆桩和尖端和侧灌浆桩的承诺89.6类似于91.3%,94.6%,92.4%,93.0%,95.7分别占总加载的百分比。最后,采用了参数回分析方法和数值计算来预测深厚软土中取代钻孔桩的长期沉降特性。确定的体积模量(K)和蠕变参数(K-S)用于后灌浆桩的长期沉降的后面分析。后分析和测量数据之间的定居差约为1.11%-7.41%。后灌浆桩的长期沉降是通过后分析方法预测的,并且预测结果表明,灌浆后桩的沉降小于6毫米,30天内将稳定。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号