Challenging issues in the design and manufacturing of the European sectors of the ITER vacuum vessel

机译:ITER真空容器欧洲地区设计和制造中的难题

获取原文
获取原文并翻译 | 示例
       

摘要

Fusion for Energy (F4E), the European Domestic Agency for the ITER project, has to supply seven sectors as part of the European contribution to the project. F4E signed the Procurement Agreement with ITER Organization (IO) in 2009. After a call for tender in 2010, the contract for the manufacturing of seven sectors was placed in October 2010 to a consortium of three Italian companies, Ansaldo, Mangiarotti and Walter Tosto (AMW). The first sector in the manufacturing route is Sector 5 (later will come 4,3,2,9,8, 7). This paper will cover: the status of the engineering activities, design, procurement and preparation to begin the manufacturing in 2013. Also will be presented the statutory and regulatory requirements of the French Nuclear Safety regulator and the status of the relevant R&D mock-ups to demonstrate manufacturing feasibility control of distortions (using predictions with analysis and algorithms to change in real time the manufacturing route in order to correct such distortions, inspectability and metrology). Another important aspect at this stage of the manufacturing is qualification of activities like welding, Non-destructive Examination and Hot Forming. This paper describes the status of the activities currently in process in order to meet with the challenging design, schedule and high quality requirements of the project.
机译:作为ITER项目的欧洲国内机构,Fusion for Energy(F4E)必须提供七个部门作为欧洲对该项目的贡献。 F4E于2009年与ITER组织(IO)签订了采购协议。在2010年进行招标后,2010年10月,由七个意大利公司Ansaldo,Mangiarotti和Walter Tosto组成的财团与七个工业部门签订了制造合同( AMW)。制造路线中的第一个部门是部门5(以后将是4,3,2,9,8,7)。本文将涵盖:从2013年开始制造的工程活动,设计,采购和准备工作的状态。还将介绍法国核安全监管机构的法规和监管要求以及与之相关的研发模型的现状。演示变形的制造可行性控制(使用带有分析的预测和算法实时更改制造路线,以纠正这种变形,可检查性和度量衡)。在制造阶段的另一个重要方面是对焊接,无损检测和热成型等活动进行鉴定。本文描述了当前正在进行的活动的状态,以便满足具有挑战性的设计,进度和项目的高质量要求。

著录项

  • 来源
    《Fusion Engineering and Design》 |2014年第8期|1769-1774|共6页
  • 作者单位

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

    Fusion for Energy, C/ Josep Pla,.2, Torres Diagonal Litoral, Edificio B3, E-08019 Barcelona, Spain;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);美国《生物学医学文摘》(MEDLINE);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    ITER vacuum vessel; Manufacturing; Welding; NDE inspection;

    机译:ITER真空容器;制造业;焊接;无损检测;
  • 入库时间 2022-08-18 00:38:51

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号