Techno-economic evaluation of advanced IGCC lignite coal fuelled power plants with CO_2 capture

机译:先进的IGCC褐煤燃煤电厂的技术经济评估

获取原文
获取原文并翻译 | 示例
           

摘要

The techno-economic evaluation of four novel integrated gasification combined cycle (IGCC) power plants fuelled with low rank lignite coal with CO_2 capture facility has been investigated using ECLIPSE process simulator. The performance of the proposed plants was compared with two conventional IGCC plants with and without CO_2 capture. The proposed plants include an advanced CO_2 capturing process based on the Absorption Enhanced Reforming (AER) reaction and the regeneration of sorbent materials avoiding the need for sulphur removal component, shift reactor and/or a high temperature gas cleaning process. The results show that the proposed CO_2 capture plants efficiencies were 18.5-21% higher than the conventional IGCC CO_2 capture plant. For the proposed plants, the CO_2 capture efficiencies were found to be within 95.8-97%. The CO_2 capture efficiency for the conventional IGCC plant was 87.7%. The specific investment costs for the proposed plants were between 1207 and 1479€/kW_e and 1620€/kW_e and 1134 €/kW_e for the conventional plants with and without CO_2 capture respectively. Overall the proposed IGCC plants are cleaner, more efficient and produce electricity at cheaper price than the conventional IGCC process.
机译:利用ECLIPSE过程模拟器,对四台新型的低阶褐煤加CO_2捕集装置供气的新型联合气化联合循环(IGCC)电厂进行了技术经济评价。将拟议的电厂的性能与具有和不具有CO_2捕集的两种常规IGCC电厂进行了比较。拟议的工厂包括基于吸收增强重整(AER)反应的先进CO_2捕集工艺和吸附剂材料的再生,从而无需硫去除组分,变换反应器和/或高温气体净化工艺。结果表明,拟议的CO_2捕集装置效率比常规IGCC CO_2捕集装置高18.5-21%。对于拟议的工厂,发现CO_2的捕集效率在95.8-97%之内。常规IGCC工厂的CO_2捕集效率为87.7%。对于具有和不具有CO_2捕集的常规工厂,拟建工厂的具体投资成本分别在1207至1479€/ kW_e和1620€/ kW_e和1134€/ kW_e之间。总体而言,与传统的IGCC工艺相比,拟议的IGCC工厂更清洁,更高效并且以更低的价格发电。

著录项

  • 来源
    《Fuel》 |2009年第12期|2495-2506|共12页
  • 作者单位

    School of the Built Environment, Centre for Sustainable Technologies, University of Ulster, Co Antrim, BT37 0QB, Northern Ireland, United Kingdom;

    School of the Built Environment, Centre for Sustainable Technologies, University of Ulster, Co Antrim, BT37 0QB, Northern Ireland, United Kingdom;

    School of the Built Environment, Centre for Sustainable Technologies, University of Ulster, Co Antrim, BT37 0QB, Northern Ireland, United Kingdom;

    School of the Built Environment, Centre for Sustainable Technologies, University of Ulster, Co Antrim, BT37 0QB, Northern Ireland, United Kingdom;

    School of the Built Environment, Centre for Sustainable Technologies, University of Ulster, Co Antrim, BT37 0QB, Northern Ireland, United Kingdom;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    integrated gasification combined cycle; (IGCC); CO_2 capture and storage (CCS); techno-economic; emissions; power plant;

    机译:整体气化联合循环;(IGCC);CO_2捕获和储存(CCS);技术经济排放发电厂;

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号