The owners of three large nuclear units in New Jersey plan to spend more than $800 million over the next five years on engineering and construction to correct nagging problems at the facilities, upgrade the units, and improve their reliability and profitability. Work on the 1,049-MW Hope Creek unit began this month. The two-unit, 2,212-MW Salem nuclear station will also be improved in the program. Both plants share a site on the lower Delaware River, in Salem County, N.J.
机译:新泽西州三个大型核装置的所有者计划在未来五年内花费8亿多美元用于工程和建设,以纠正设施上的na问题,升级装置并提高其可靠性和盈利能力。 1,049兆瓦的Hope Creek机组的工作于本月开始。该计划还将改进两座2212兆瓦塞勒姆核电站。两种植物都位于新泽西州塞勒姆县的特拉华河下游。