Project Performance Evaluation using EVA Technique: Kotay Bridge Construction Project on Kayto River in Afghanistan

机译:使用EVA技术的项目性能评估:阿富汗凯托河Kotay桥梁建设项目

获取原文
           

摘要

The objective of the study is the assessment of an operating bridge project in terms of its performance by the evaluate project performance (EVA) technique. To apply the EVA technique, cost and schedule baselines and an update record of performed work with spent money is prepared for the project. The data is taken directly from site office of the project. Kotay bridge construction project is selected for case study. Project tracking is achieved by taking EVA technique to assess the Kotay bridge construction project performance in the last five months, and to find out the cost and time overruns if they exist. The Estimation at Completion (EAC) and To-Complete Performance Index (TCPI) are found as well to know how efficiently are used the remaining financial resources. The study revealed that CPI and SPI are both less than 1.0, which means that the project could not be performed well. Costandtime overruns are clearly indicated as well.
机译:该研究的目的是通过评估项目性能(EVA)技术在其性能方面评估运营桥梁项目。 为了应用EVA技术,为该项目准备了花费的成本和计划基线和已执行的工作的更新记录。 数据是直接从项目的现场办公室进行。 选择Kotay桥梁建设项目以供案例研究。 通过采用EVA技术在过去五个月中评估Kotay桥梁建设项目性能,并找出如果存在的成本和时间过度,则实现项目跟踪。 找到完成(EAC)和完整的性能指数(TCPI)的估计,也可以了解如何使用剩余的财务资源。 该研究表明,CPI和SPI均小于1.0,这意味着该项目无法康复。 Cortandtime超支也明确表明。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号