Corruption Risk Analysis at the Project Planning Stage in the Iraqi Construction Sector using the Bowtie Methodology

机译:利用Bowtie方法的伊拉克建筑业项目规划阶段腐败风险分析

获取原文
           

摘要

In this paper, the bowtie method was utilized by a multidisciplinary team in the Federal Board of Supreme Audit (FBSA)for the purpose of managing corruption risks threatening the Iraqi construction sector. Corruption in Iraq is a widespread phenomenon that threatens to degrade society and halt the wheel of economic development, so it must be reduced through appropriate strategies. A total of eleven corruption risks have been identified by the involved parties in corruption and were analyzed by using probability and impact matrix and their priority has been ranked. Bowtie analysis was conducted on four factors with high score risk in causing corruption in the planning stage. The number and effectiveness of the existing proactive measures to prevent threats from resulting in corruption and were examined for each threat.
机译:在本文中,由最高审计(FBSA联邦委员会的多学科团队(FBSA)利用Bowtie方法,以管理威胁伊拉克建设部门的腐败风险。 伊拉克的腐败是一种广泛的现象,可能威胁要降低社会并停止经济发展之轮,因此必须通过适当的策略减少。 腐败方共有11个腐败风险,并通过使用概率和影响矩阵进行分析,并排名第一。 蝴蝶结分析在四个因素进行了高分风险,导致规划阶段损坏。 现有积极措施的数量和有效性,以防止威胁导致腐败,并对每种威胁进行审查。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号