Scheduling of Empennage Structure Design Project of Indonesia’s Aircraft with Critical Path Method (CPM)

机译:临界路径方法(CPM)印度尼西亚飞机Empennage结构设计项目的调度

获取原文
   

获取外文期刊封面封底 >>

       

摘要

Production of the aircraft becomes very important to facilitate many passengers of aircraft in Indonesia in the future. The design of a very complex aircraft requires proper project management. This study aims to perform the best scheduling project of empennage structure design of Indonesia’s aircraft with limited resources. Critical Path Method (CPM) is used to schedule the project based on activity and resource. CPM scheduling results in completion time for activity data for 400 working days. CPM scheduling after assigning human resources results in a longer completion time for 1023.47 working days. CPM scheduling is carried out by reallocating of human resources to produce a shorter completion time, and it results in completion time for 955 working days.
机译:飞机的生产变得非常重要,便于在未来在印度尼西亚的许多飞机乘客。一架非常复杂的飞机的设计需要适当的项目管理。本研究旨在为印度尼西亚飞机的Empennage结构设计进行最佳调度项目,资源有限。关键路径方法(CPM)用于根据活动和资源安排项目。 CPM调度在400个工作日的活动数据完成时间的结果。分配人力资源后的CPM调度导致1023.47个工作日的更长的完成时间。 CPM调度是通过重新分配人力资源来产生更短的完成时间来进行的,并且它会导致完成时间955个工作日。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号