The effects of drying time during manufacturing process on partial discharge of 83.3 mva 275/160 kv power transformer

机译:制造过程中干燥时间对83.3 mva 275/160 kv电力变压器局部放电的影响

获取原文
   

获取外文期刊封面封底 >>

       

摘要

Power transformer (PT), essential equipment in electrical power system proceeds complicated manufacturing process to meet high standard design. During manufacturing process of PT, the drying stage is of importance to remove excessive moisture contaminant on the solid insulation. This study investigated the effects of drying duration on partial discharge test of 83.3 MVA 275/160 kV PT. The partial discharge test measurements were carried out using IEC 60270 standards comprising of the capacitive network model based on the main quantity apparent charge concept. We found that the lowest partial discharge of 21 pC was achieved at 68 hours drying duration, while the highest value of 60 pC was reached at 81 hours drying time. The longer drying time may lead to initial degradation of cellulose insulation due to excessive heating. The amount of water extracted during drying effect to partial discharge also investigated. We conclude that the drying time at a higher and lower than 68 hours significantly contributes to the increased partial discharge values of PT.
机译:电力变压器(PT)是电力系统中必不可少的设备,其制造过程复杂,以满足高标准设计要求。在PT的制造过程中,干燥阶段对于去除固体绝缘材料上过多的水分污染物很重要。这项研究调查了干燥时间对83.3 MVA 275/160 kV PT的局部放电测试的影响。局部放电测试测量是使用IEC 60270标准进行的,该标准包括基于主要视在电荷概念的电容网络模型。我们发现,在68小时的干燥时间下实现了最低的21 pC局部放电,而在81小时的干燥时间下达到了60 pC的最高值。较长的干燥时间可能会由于过度加热而导致纤维素绝缘材料的初始降解。还研究了干燥过程中对局部排放的提取水量。我们得出的结论是,高于和低于68小时的干燥时间会显着增加PT的局​​部放电值。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号