An ex ante control chart for project monitoring using earned duration management observations

机译:使用获得的工期管理观察值进行项目监控的事前控制图

获取原文
       

摘要

In the past few years, there has been an increasing interest in developing project control systems. The primary purpose of such systems is to indicate whether the actual performance is consistent with the baseline and to produce a signal in the case of non-compliance. Recently, researchers have shown an increased interest in monitoring project’s performance indicators, by plotting them on the Shewhart-type control charts over time. However, these control charts are fundamentally designed for processes and ignore project-specific dynamics, which can lead to weak results and misleading interpretations. By paying close attention to the project baseline schedule and using statistical foundations, this paper proposes a new ex ante control chart which discriminates between acceptable (as-planned) and non-acceptable (not-as-planned) variations of the project’s schedule performance. Such control chart enables project managers to set more realistic thresholds leading to a better decision making for taking corrective and/or preventive actions. For the sake of clarity, an illustrative example has been presented to show how the ex ante control chart is constructed in practice. Furthermore, an experimental investigation has been set up to analyze the performance of the proposed control chart. As expected, the results confirm that, when a project starts to deflect significantly from the project’s baseline schedule, the ex ante control chart shows a respectable ability to detect and report right signals while avoiding false alarms.
机译:在过去的几年中,对开发项目控制系统的兴趣日益增加。这种系统的主要目的是指出实际性能是否与基准一致,并在不遵守规定的情况下发出信号。最近,研究人员对监控项目的绩效指标表现出了越来越浓厚的兴趣,可以将它们绘制在Shewhart型控制图上,随着时间的推移。但是,这些控制图从根本上是为过程设计的,并且忽略了特定于项目的动态,这可能导致结果不佳和误导性的解释。通过密切关注项目基准进度表并使用统计基础,本文提出了一个新的事前控制图,用于区分项目进度绩效的可接受(按计划)和不可接受(不按计划)变化。这样的控制图使项目经理可以设置更现实的阈值,从而为采取纠正和/或预防措施做出更好的决策。为了清楚起见,已经给出了说明性示例以示出实践中如何构造事前控制图。此外,已进行实验研究以分析所建议控制图的性能。正如预期的那样,结果证实,当一个项目开始偏离项目的基线进度时,事前控制图显示出可观的能力,可以检测和报告正确的信号,同时避免误报。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号