Critical Chain Project Management Based on a Max-Plus Linear Representation for Determining Time Buffers in Multiple Projects

机译:基于Max-Plus线性表示的关键链项目管理,用于确定多个项目中的时间缓冲区

获取原文
           

摘要

We propose a framework for describing the Critical Chain Project Management (CCPM) method based on a Max-Plus Linear (MPL) representation for multiple projects. The framework takes into account time buffers in both a single and multi-project environments which play a role for controlling undesirable state change and protecting the completion time for the entire system. The appropriate position and size of these buffers are determined for a large scale multi-project system. Furthermore, the MPL system with the CCPM method applied is redefined to easily comprehend the structure of the system. Finally, we confirm the proposed framework through a numerical example.
机译:我们提出了一个框架,用于描述基于多个项目的最大加线性(MPL)表示的关键链项目管理(CCPM)方法。该框架考虑了单个项目环境和多个项目环境中的时间缓冲区,这些时间缓冲区起着控制不良状态更改并保护整个系统的完成时间的作用。对于大型多项目系统,确定这些缓冲区的适当位置和大小。此外,重新定义了应用CCPM方法的MPL系统,以轻松理解系统的结构。最后,我们通过一个数值示例来确认提出的框架。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号