Labour engagement optimization in planning the execution of river regulation works on the Jela?ni?ka river

机译:优化Jela?ni?ka河上的河道整治计划中的劳动参与

获取原文
           

摘要

A project is a task comprising a set of interrelated activities requiring time and resources for their execution. It is often the case that during the construction of longitudinal and cross section structures for the regulation of a torrential catchment the required resources (labour, materials, mechanization, and finances) are often limited and because of that we face the problem of their efficient use. This paper deals with the problem of planning the execution of river regulation works on the Jela?ni?ka River with the aim to minimize the time extension due to limited resources. In the planning phase of project realization labour force is the limited resource. Heuristic techniques, i.e. the Gray-Kidd algorithm with the use of MS Project software were applied in the distribution of resources for the purposes of optimal labour engagement. This method uses the data acquired by the CPM method of network planning as input elements. Through more iterations, by moving noncritical and then critical project activities, the minimal extension of project duration was achieved by engaging more labour force. Therefore, the proposed heuristic and CPM method performed well in resolving the resource-constrained project scheduling problem. [Projekat Ministarstva nauke Republike Srbije, br. 43007: Istra?ivanje klimatskih promena na ?ivotnu sredinu: pra?enje uticaja, adaptacija i ubla?avanje , podprojekat br. 16: Socio-ekonomski razvoj, ubla?avanje i adaptacija na klimatske promene]
机译:项目是一项任务,包括一组相互关联的活动,需要时间和资源来执行。通常情况下,在建造纵向和横截面结构以调节洪流的过程中,所需的资源(劳动力,材料,机械化和财务)经常受到限制,因此我们面临着对其有效利用的问题。 。本文讨论了计划在耶拉尼卡河上进行河道整治工程的问题,目的是最大程度地减少由于资源有限而造成的时间延长。在项目实现的计划阶段,劳动力是有限的资源。启发式技术,即使用MS Project软件的Gray-Kidd算法,被用于资源分配,以实现最佳的劳动参与。该方法将通过网络规划的CPM方法获取的数据用作输入元素。通过更多的迭代,通过移动非关键项目活动然后进行关键项目活动,可以通过增加劳动力投入来最大程度地缩短项目工期。因此,所提出的启发式和CPM方法在解决资源受限的项目调度问题方面表现良好。 [Projekat Ministarstva nauke Republike Srbije,br。 43007:Istra?ivanje klimatskih promena na?ivotnu sredinu:pra?enje uticaja,adaptacija i ubla?avanje和podprojekat br。 16:Socio-ekonomski razvoj,ubla?avanje i Adaptacija na klimatske promene]

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号