UNINTENDED NEGATIVE EFFECTS OF CLIENT PROJECT COST CONTROLS: A SYSTEM DYNAMICS APPROACH

机译:客户项目成本控制的意外负面影响:一种系统动力学方法

获取原文
           

摘要

Project controls have been defined in the existing literature as managerial decisions and actions aimed at rectifying poor project performance. Understanding the potential unintended negative effects of such controls will be beneficial to project management practice and to the resulting project performance. Using the system dynamics approach, this article investigates some unintended negative effects of client project cost controls. Empirical data from a raw-water infrastructure project are used to calibrate the formulated system dynamics simulation model. Simulation results suggest that the client project cost controls (aimed at minimising project cost), unintentionally generate some counteractive effects (an increase in the project cost and the time schedule duration).
机译:现有文献中已将项目控制定义为旨在纠正不良项目绩效的管理决策和行动。理解此类控制的潜在的意想不到的负面影响将有益于项目管理实践以及由此产生的项目绩效。本文使用系统动力学方法,研究了客户项目成本控制的一些意想不到的负面影响。来自原水基础设施项目的经验数据用于校准公式化的系统动力学仿真模型。仿真结果表明,客户项目成本控制(旨在最小化项目成本)无意间产生了一些反作用(项目成本和时间表持续时间的增加)。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号