Design and construction of an anchored soldier pile wall for a large underground car park

机译:大型地下停车场的锚兵墙设计与施工

获取原文
       

摘要

The geotechnical conditions of the soil and the construction conditions of a retained wall for an underground car park project of two levels are described. The project is located in the centre of the city of Concepción, south of Chile. The excavation support had to avoid any damage of the Tribunals of Justice historic building and the surrounding buildings. Other buildings have between four and nine floors and the Hites building is also classified as a historical building. Also, it has to be included the avoidance of any interference with facilities and services such as water, sewage, gas and electricity. The solution adopted was an anchored soldier pile wall of 8 m of depth around the excavation, where the soldier piles (H section steel piles) were driven into semi dense silty sand. Two lines of anchors were designed separated vertically and horizontally 3 m and 3.2 m respectively. The design loads for the anchors were calculated between 300 and 560 kN. In particular, the anchors installation and placement were studied in order to not disturb the different stages of construction. The project included 3596 m 2 of anchored soldier pile wall with 314 post-stressed anchors and 300 soldier piles totalling 3200 m. It is concluded that the temporary excavation support solution adopted performed adequately to the intricate conditions, since no observable deformation in the Tribunals nor in the surrounding buildings nor in the services occurred during construction. Concepción city was severely struck by an 8.8 moment magnitude earthquake on the 27 th February 2010. The construction of the underground car park was just ready when the earthquake occurred. No damage was observed in the car park due to the seismic event. It is believed that the buried soldier pile wall may reduce seismic loadings acting on the underground car park structure since no evidence of damage exists after the very big earthquake.
机译:描述了地下停车场项目两层的土壤岩土条件和挡土墙的施工条件。该项目位于智利南部的康塞普西翁市中心。挖掘支持必须避免对法庭的历史建筑和周围建筑物造成任何破坏。其他建筑物的楼层在4到9层之间,而Hites大楼也被列为历史建筑物。此外,还必须包括避免对设施和服务(如水,污水,天然气和电力)的任何干扰。所采用的解决方案是在开挖周围的8 m深度处锚固一排士兵桩墙,将士兵桩(H型钢桩)打入半致密粉砂中。设计了两排锚,分别在垂直和水平方向分开3 m和3.2 m。计算出的锚的设计载荷在300至560 kN之间。特别是,对锚的安装和放置进行了研究,以免干扰施工的不同阶段。该项目包括3596 m 2的锚兵墙和314个预应力锚,以及300个兵桩,总计3200 m。可以得出结论,由于在建造过程中在法庭,周围建筑物或服务中均未观察到变形,所采用的临时开挖支持解决方案在复杂的条件下表现良好。康塞普西翁市在2010年2月27日遭受了8.8级大地震的严重打击。地震发生时,地下停车场的建设就已经准备就绪。在地震中未在停车场发现损坏。可以相信,埋在地下的士兵桩墙可以减少作用在地下停车场结构上的地震荷载,因为在非常大的地震之后没有损坏的迹象。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号