> Problem statement: Damage due to corrosion is a significant problem worldwide. Countries around the world have estimated that the cost of corrosion to their national economies to be 3-4% of their gross national product. Approach: Design and implementation a new steel piling of the Corrosion Management Program (CMP) in Al-Zubare harbor. Corrosion management algorithm can be divided into three major phases. Phase 1 of the program is the programmatic assessment of the project. Phase 2 of the program involves physical assessment and actual remediation. Phase 3 of the program mainly deals with future monitoring of the repaired structure. Results: The CMP included activities performed to mitigate corrosion, to repair corrosion-induced damage and to replace the structures that are badly corroded. Installation and maintenance requirements are identified.
Conclusion: The data was collected from the tide table for Al-Zubare Harbor in the year 2004. The highest tide of the year would fall on 17 October 2004 at 1.05 am with level 3.5 m, while the lowest tide of the year would fall on 3 July 2004 at 5.13 am with level 0m. The detection results show that this program is feasible and effective.
机译: > 问题陈述:腐蚀造成的损坏是世界范围内的重大问题。据世界各国估计,腐蚀对本国经济造成的损失占其国民生产总值的3-4%。方法:设计并实施腐蚀管理计划(CMP)的新钢桩)在Al-Zubare港口。腐蚀管理算法可分为三个主要阶段。该计划的第一阶段是对该项目的计划评估。该计划的第二阶段涉及身体评估和实际补救。该计划的第3阶段主要涉及对修复后的结构的未来监视。结果: CMP包括为减轻腐蚀,修复腐蚀引起的损坏以及替换严重腐蚀的结构而进行的活动。确定了安装和维护要求。
结论:数据是从2004年Al-Zubare港口的潮汐表中收集的。该年度的最高潮汐发生在2004年10月17日。最高潮为1.05上午,高度为3.5 m,而今年的最低潮将落在2004年7月3日凌晨5.13,高度为0m。检测结果表明该程序是可行和有效的。