Impact of Personnel Factors on the Recovery of Delayed Software Projects: A System Dynamics Approach

机译:人为因素对延迟软件项目的恢复的影响:系统动力学方法

获取原文
       

摘要

Delay in a software project may result in the loss of a market opportunity or the postponement of a dependent project. Therefore, software project managers take various steps to ensure that their project is completed on time, such as adding new members to the project team. However, adding new manpower to a delayed project may cause a negative impact on the teama??s productivity due to assimilation time, training overhead and communication overhead. Consequently, project managers have difficulty in making the decision on whether or not to add new members to the team. Thus, this research aims to examine whether a significant schedule improvement can be achieved with consideration of the new manpowera??s capabilities, skills and experience. A System Dynamics Model is proposed to simulate the behaviour of a projecta??s progress when new members are added. The proposed model was evaluated through experiments using two types of case studies. The results of the experiments indicate that a significant schedule improvement of a late project can be achieved if people with certain levels of personnel factors are added to the project.
机译:软件项目的延迟可能会导致失去市场机会或推迟从属项目。因此,软件项目经理将采取各种步骤来确保其项目按时完成,例如将新成员添加到项目团队中。但是,由于同化时间,培训开销和通信开销,为延迟的项目增加新的人力可能会对团队的生产力造成负面影响。因此,项目经理很难决定是否向团队中添加新成员。因此,这项研究的目的是检验在考虑新的人力资源的能力,技能和经验的情况下是否可以实现重大的进度改进。提出了一个系统动力学模型来模拟新成员添加时项目进度的行为。通过使用两种类型的案例研究通过实验评估了建议的模型。实验结果表明,如果将具有一定水平的人为因素的人添加到项目中,则可以显着改善后期项目的进度。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号