首页> 外文期刊>Construction News >A fine point can scupper adjudication
【24h】

A fine point can scupper adjudication

机译:罚款可以削弱裁决

获取原文
获取原文并翻译 | 示例
           

摘要

The refusal by the Technology and Construction Court to enforce the adjudicator's decision in CJP v Verry earlier this month shows the legal ambiguity that can exist in such cases. The case revolved around a dispute between brickwork subcontractor CJP and building contractor William Verry. CJP wished to adjudicate an interim payment claim in the order of £100,000 and the rules of the subcontract stated that Verry had seven days in which to produce written submissions. Verry sought extra time to make its submissions, asking for 17 days. An agreed time and date for the submission was negotiated but Verry handed the submissions in at 5.30 pm on this date, after the agreed submission deadline of noon.
机译:技术和建设法院本月初在CJP诉Verry案中拒绝执行判决人的裁决,显示了此类案件中可能存在的法律歧义。该案涉及砖瓦分包商CJP与建筑承包商William Verry之间的纠纷。 CJP希望裁定100,000英镑的临时付款索赔,并且分包合同的规则规定,Verry有7天的时间提交书面意见。 Verry要求额外的时间进行提交,要求17天。商定了提交的商定时间和日期,但是Verry在约定的提交截止时间中午之后的该日期的5.30 pm提交了提交。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号