首页> 外文期刊>Civil Eengineering >Lateral support for cuts and fills on National Route 1, Section 21, between Lynnwood Road and Rigel Avenue
【24h】

Lateral support for cuts and fills on National Route 1, Section 21, between Lynnwood Road and Rigel Avenue

机译:在林恩伍德路和里格尔大道之间的21号国道1号线,为挖方和填方提供横向支撑

获取原文
获取原文并翻译 | 示例
           

摘要

Soil nails were installed as excavation proceeded. The face of the cutting was initially machine excavated, but final trimming was done by hand. Once the lines and levels to the tolerances of +0 mm (i.e. towards the outside of the face) to -50 mm (i.e. into the soil face) had been attained, the drainage strip was applied, followed by a flash coat, 25 mm thick. The holes for the soil nails were drilled through the flash coat and the grout pumped into each hole from the base of the hole so as to ensure that the complete hole was filled with grout. When the grout overflowed from the face of the hole, the soil nails were installed with spacers to ensure that they were centrally located within the holes. Where the soil face was very stable, this procedure was altered to suit the contractor's requirements in that the soil nail and grout were in some cases installed prior to the application of the flash coat.
机译:在开挖过程中安装土钉。切割的表面最初是用机器开挖的,但是最后的修剪是手工完成的。一旦达到的线和水平达到+0毫米(即朝向表面的外侧)至-50毫米(即进入土壤表面)的公差,则应用排水条,然后进行25毫米的防水层厚。在防水层上钻出用于钉子的孔,然后将水泥浆从孔的底部泵入每个孔中,以确保整个水泥浆都充满了水泥浆。当灌浆从孔的表面溢出时,将土钉安装有垫片,以确保它们位于孔的中心。在土壤面非常稳定的地方,为了适应承包商的要求,对该程序进行了更改,因为在某些情况下,在应用防水涂料之前已安装了土壤钉子和水泥浆。

著录项

  • 来源
    《Civil Eengineering》 |2009年第3期|21-24|共4页
  • 作者

    Alan Parrock;

  • 作者单位

    Geotechnicai Principal ARQ Consulting Engineers (Pty) Ltd;

  • 收录信息 美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词