Construction commenced on 19 April 2014 and practical completion of the main contract ended on 27 February 2015. The main building contract had several sectional completion dates, with partial handovers to the client. This allowed Toyota South Africa Motors to begin with the press installation, while construction was still under way. The project was completed on time and within budget, at a final construction cost of R133.8 million.