Development of automated change order impact detection and quantification system

机译:开发自动化变更单影响检测和量化系统

获取原文
获取原文并翻译 | 示例
           

摘要

When change orders occur, adjustments in contract price and duration are usually agreed upon through negotiation or stipulated by contract terms and conditions. There are many pricing methods for change orders impact on productivity loss available, but negotiations using these methods do not always result in a contractor and client agreement. The most difficult issue to agree upon is how to quantify the cumulative impact of change orders on overall construction project. Cumulative impact claims imply that the disruption caused by a single change can have a ripple effect on the entire project, beyond the change itself. In order to recover cumulative impact damages, by law, the contractor is required to prove three basic components: liability, causation, and resultant injury (quantum). Of these elements, causation and resultant injury are the most difficult to prove. There has been some research performed to quantify the cumulative impact of change orders on labor productivity. CI1 and the University of Wisconsin have performed the most recent and extensive study related to this issue. This study used previous CII-Hanna research models to develop an automated system for the detection and quantification of change order impacts. In addition, a project demonstration is included to allow easy understanding for new system users. The developed system provides a simple guide for stakeholders to expedite the resolution of change order related disputes between contractors and owners by providing causation and resultant injury(quantum) analysis on troubled projects.
机译:当发生变更单时,合同价格和期限的调整通常是通过协商达成协议或由合同条款和条件规定的。变更单影响可用生产力的定价方法有很多,但是使用这些方法进行的谈判并不总是能达成承包商与客户的协议。要达成共识的最困难的问题是如何量化变更单对总体建设项目的累积影响。累积影响声明暗示,由单个更改引起的中断可能会对整个项目产生连锁影响,而不仅仅是更改本身。为了追回累积的撞击损失,法律要求承包商证明三个基本组成部分:责任,因果关系和由此造成的伤害(量子)。在这些要素中,因果关系和由此造成的伤害最难以证明。已经进行了一些研究来量化变更单对劳动生产率的累积影响。 CI1和威斯康星大学进行了与此问题相关的最新,最广泛的研究。该研究使用以前的CII-Hanna研究模型来开发用于检测和量化变更单影响的自动化系统。此外,还包括一个项目演示,以使新系统用户容易理解。所开发的系统通过为有问题的项目提供因果关系和由此产生的伤害(量子)分析,为利益相关者提供一个简单的指南,以加快解决承包商与业主之间与变更单相关的纠纷。

著录项

  • 来源
    《Automation in construction》 |2009年第5期|525-535|共11页
  • 作者单位

    Dept. of Civil Engineering, Chungnam National University, 220 Gung-dong, Yuseong-gu, Daejeon, 305-764, South Korea;

    Dept. of Construction Science, Texas A &M University, 3137 TAMU, College of Architecture. Texas A&M University, College Station, Texas 77843-3137, United States;

    Del E. Webb School of Construction, Arizona State University, Tempe, Arizona 85287, United States;

    Dept. of Civil and Envir. Engrg., Univ. of Wisconsin-Madison, 2314 Engrg. Hall, 1415 Engrg, Dr., Madison, Wl 53706, United States;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    change orders; productivity impact; detection and quantification system;

    机译:更改订单;生产力影响;检测定量系统;

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号