BIM-based estimation of vertical transportation demands during the construction of high-rise buildings

机译:基于BIM的高层建筑施工期间垂直运输需求的估算

获取原文
获取原文并翻译 | 示例
           

摘要

The temporary vertical transportation systems used during the construction of high-rise buildings, including tower cranes, temporary elevators, and concrete pumps, have a significant effect on the cost of a project. If they are under designed, they lead to project delays, which are expensive. If they are over designed, then they cost more to construct than necessary. The accurate estimation of vertical transportation demands is necessary to optimally determine the temporary vertical transportation systems required. The current demand estimation process is mostly manual and, therefore, time-consuming and prone to errors. In this paper, a methodology to estimate vertical transportation demands during the construction of high-rise buildings is proposed, that is automated and, therefore, both faster and less prone to errors than the current manual process. The methodology exploits building information modeling (BIM), and improves estimates by explicitly considering (1) the demands related to the transportation of temporary construction systems (i.e., formwork, shoring and scaffolding systems), auxiliary construction resources (e.g., tools, equipment), construction waste, and construction workers, (2) the demands in different construction zones, (3) the demands for inter-floor transportation and transportation to non-construction locations, (4) the demands handled by all vertical transportation systems, and their availability in these over time. Four items that have not been simultaneously considered in previous research. The methodology is demonstrated by using it to estimate the vertical transportation demands for the construction of a 36-story high-rise reinforced concrete building. It is shown that the new process is faster and more accurate, and can be easily adjusted to account for changes.
机译:高层建筑施工中使用的临时垂直运输系统,包括塔式起重机,临时电梯和混凝土泵,对项目成本有重大影响。如果设计不当,则会导致项目延误,这很昂贵。如果它们被过度设计,那么它们的建造成本将超出必要。为了最佳地确定所需的临时垂直运输系统,必须对垂直运输需求进行准确的估算。当前的需求估算过程大部分是手动的,因此很耗时且容易出错。在本文中,提出了一种用于估计高层建筑施工期间垂直运输需求的方法,该方法是自动化的,因此比当前的手动过程更快且更不容易出错。该方法利用建筑信息模型(BIM),并通过明确考虑(1)与临时建筑系统(即模板,支撑和脚手架系统),辅助建筑资源(例如工具,设备)的运输相关的需求来改进估算,建筑废物和建筑工人;(2)不同建筑区域的需求;(3)楼层间运输和非建筑地点运输的需求;(4)所有垂直运输系统处理的需求及其这些随时间的可用性。在以前的研究中没有同时考虑的四个项目。通过使用该方法估算36层高层钢筋混凝土建筑的垂直运输需求,证明了该方法。结果表明,新过程更快,更准确,并且可以轻松调整以适应变化。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号