The end of power operation of a nuclear power plant is followed either by safe enclosure and later demolition, or immediate dismantling and demolition. In the latter case, measures should be taken at the onset of the decommissioning phase to minimize the costs of operation of the infrastructure required during the disassembly phase (residual operation), thus allowing speedy disassembly over large areas of systems and components no longer required.
机译:核电厂的电力运营结束后,将安全围封并随后进行拆除,或者立即进行拆除和拆除。在后一种情况下,应在退役阶段开始时采取措施,以最小化拆卸阶段所需的基础设施的运营成本(剩余运行),从而在不再需要的大面积系统和组件上快速拆卸。