Applying Local Rescheduling in response to schedule disruptions

机译:应用本地重新计划以响应计划中断

获取原文
获取原文并翻译 | 示例
获取外文期刊封面目录资料

摘要

In realistic scenarios of disruption management the high number of potential options makes the provision of decision support-on how to get back on track-complex. It is thus desirable to reduce the size of the regarded problems by applying methods of partial rescheduling. As existing approaches (such as Affected Operations Rescheduling or Matchup Scheduling) mainly focus on production-specific problems, we propose Local Rescheduling (LRS) as a generic approach to partial rescheduling in this paper. It integrates previous research on partial rescheduling and local search in the context of complex project scheduling problems. LRS is based on the bidirectional incremental extension of a time window regarded for potential schedule modifications. Experiments show that LRS outperforms previous approaches.
机译:在实际的中断管理方案中,大量的潜在选择为如何恢复复杂轨道提供了决策支持。因此,期望通过应用部分重新调度的方法来减小所考虑的问题的大小。由于现有方法(例如“受影响的操作重新安排”或“对接安排”)主要关注特定于生产的问题,因此,本文提出了局部重新安排(LRS)作为部分重新安排的通用方法。它在复杂的项目计划问题的背景下,整合了先前有关部分计划和局部搜索的研究。 LRS基于时间窗口的双向增量扩展,该时间窗口被视为可能进行时间​​表修改。实验表明LRS优于以前的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号