Setting safety lead-times for purchased components in assembly systems: a general solution procedure

机译:设置装配系统中已购买组件的安全交货时间:一般解决方案

获取原文
获取原文并翻译 | 示例
           

摘要

In a recent paper, Hopp and Spearman (1993) presented a model to determine optimal lead-times for purchasing components wihere the only manufactruing operation is the final assembly. It is assumed that delivery times of the different components are normal variates. An approximate iterative solution procedure is presented that facilitates derivation of the optimal lead-times. Based on an approximation for the delivery-time distribution, an alternative solution procedure is proposed that results in closed-from expressions for the decision variables of the problem. Both simplicity and ease of calculaton are achieve. Furthermore, the new procedure is extended to non-normal delivery-time distributions.
机译:在最近的一篇论文中,Hopp和Spearman(1993)提出了一个模型,用于确定购买零件的最佳提前​​期,而唯一的制造工序是最终组装。假设不同组件的交付时间是正态变量。提出了一种近似的迭代求解程序,该程序有助于推导最佳提前期。基于交货时间分布的近似值,提出了一种替代的求解过程,该过程导致问题决策变量的封闭表达式。计算既简单又容易。此外,新程序已扩展到非正常的交货时间分配。

著录项

  • 来源
    《IIE Transactions》 |1995年第5期|p.634-637|共4页
  • 作者

    HAIM SHORE;

  • 作者单位

    Department to Industrial Engineering, Faculty of Engineering, Tel-Aviv University, Ramat-Aviv, P.O.B. 39040, Tel-Aviv 69978, Israel;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 一般工业技术;
  • 关键词