The paper studies emergent processing scheme of the vertical vice-mine hoisting system fault, describes hoisting system dismantling and recovery scheme, and finally points out that:through applying sinking winder, block and tackle and locking cable and other machines, it safely, efficiently and fast accomplishes hoisting system recovery, reduces sinking winder utilization quantity, and saves equipment transportation, instal-lation, depreciation and demolition cost as well.%对某矿副立井提升系统发生故障后的应急处置方案作了研究,阐述了提升系统拆除及恢复的方案措施,指出通过使用凿井绞车、滑轮组、锁绳器等机具,安全、高效、快速地完成了提升系统的恢复工作,减少了凿井绞车的使用数量,节约了设备运输、安装、折旧、拆除费用。