结合山西朔州某热电厂主厂房地基处理实例,介绍了该工程中主厂房布置,针对主厂房位于湿陷性黄土地区的特殊地质条件,提出了一些可行的地基处理方法,并对方案进行了比较,给出了最为经济合理的地基处理方法,为该火力发电厂主厂房的地基处理提供了依据。%Combining with the treatment scheme example of a thermal power main workshop in Shanxi Shuozhou,this paper introduced the main plant layout of this project,according to the special geological conditions of main plant located in collapsible loess area,put forward some feasible foundation treatment method,and compared the solutions,gave the most economical and reasonable foundation treatment method,provided basis for the foundation treatment of thermal power main workshop.