讨论了工件加工时间服从任意分布的随机重新排序问题,目标是使期望总完工时间最小.根据理论分析的方法,研究了工件的最优加工顺序.结果表明最短期望加工时间优先规则是使目标达到最小的策略,并由该策略得出多项式时间算法.%The stochastic rescheduling problem with the processing time from arbitrary distribution were considered, and the objective is to minimize the expected of total completion time, according to theoretical analysis method, we study optimal order of job. The result show that Shortest Expected Processing Time First rule is policy that to minimize objective, and given polynomial time algorithm.