In Japan, 3-lane highway is building by Japan Highway Public Corporation. The area of 3-lane tunnel rncross-section is about 200m2 and is about 2 times as large as the cross-sectional area of a standard rnmountain tunnel in Japan. The tunnel construction method of excavation with which TBM (Tunnel rnBoring Machine) drift tunnel (the diameter is 5m) is made preceding was newly adopted as the standard rnexcavation method of mountain tunnel. Then the cross-section of its TBM drift tunnel is enlarging by rnexcavation of NATM. In order to measure all displacement of axial direction of tunnel continually rnduring excavation, the deformation is monitored inside TBM drift tunnel until the enlarged excavation rnreached. When the enlarged tunnel face arrived just before monitoring point, the measuring points have rnplaced inside wall of enlarged tunnel at less than one-cycle length. Then displacement is measured rncontinually. Therefore, to predict of natural ground behavior after enlarged becomes possible, utilizing rndeformation measurement in TBM drift tunnel, on the basis of behavior of excavated natural ground. By rncontinuous deformation measuring from the enlarge excavation before and after, continuous estimation rnof natural ground behavior, prediction generally the last displacement from displacement of enlarge rnexcavation immediately and evaluation the good or bad condition of tunnel face and natural ground rnahead of face relatively become possible. Besides effect of TBM drift tunnel thought about heretofore, rnpossible to add role of estimate of mechanical property of natural ground, evaluate behavior of natural rnground ahead of face before enlarge excavation, necessity examination of simple reinforcement and rnauxiliary method get possible.
机译:在日本,日本高速公路公共公司正在建设三车道高速公路。三车道隧道的横截面积约为200平方米,约为日本标准山隧道的横截面积的2倍。作为山区隧道的标准开挖方法,新采用了先行采用TBM(直径为5m)的漂移隧道的开挖隧道施工方法。然后,由于NATM的开挖,其TBM漂移隧道的横截面不断扩大。为了测量开挖过程中隧道轴向的所有位移,在TBM漂移隧道内部监测变形,直到到达扩大的开挖为止。当扩大的隧道面刚好到达监测点之前时,测量点已放置在扩大的隧道内壁上,且长度小于一周期。然后连续测量位移。因此,根据挖掘出的自然地面的行为,利用TBM漂移隧道中的变形测量​​来预测扩大后的自然地面行为成为可能。通过从扩大开挖前后的连续变形测量,连续估算自然地层的行为,一般立即根据扩大开挖的位移预测最后的位移,并相对地评价隧道工作面和自然面的好坏条件成为可能。除了以前考虑的TBM漂流隧道的影响外,不可能增加自然地基力学性能的估计作用,在扩大开挖之前评估自然地基在工作面之前的行为,可以进行简单加固和辅助方法的必要性检验。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号