A CASE STUDY OF REMEDIAL ACTION AND CLOSURE AT A FORMER MANUFACTURED GAS PLANT SITE

机译:一家以前制造的天然气厂的补救措施和关闭的案例研究

获取原文

摘要

This paper addresses the remediation of a former Manufactured Gas Plant (MGP) Site in western Massachusetts. The Site was located approximately 500 feet from two municipal wellheads and surrounded by residential dwellings. Contamination consisted of Polynuclear Aromatic Hydrocarbons (PAHs) and Volatile Organic Hydrocarbons (VOCs) within soils above a clay layer. Contaminated soil depths ranged from 2 to 20 feet below ground surface (bgs). The remediation included the excavation of approximately 26,000 square feet (SF) of a wetland and 8,500 SF of buffer zone soils. The soils were treated by thermal desorption and off site disposal and the wetland and buffer zone were restored. Groundwater remediation was achieved by a combination of source area removal and natural attenuation as part of a Monitored Natural Attenuation (MNA) plan. Site closure maximized the risk reduction and resulted in a condition of No Significant Risk under current conditions for a residential exposure scenario.
机译:本文介绍了在马萨诸塞州西部的一家以前的天然气工厂(MGP)场址的补救措施。该工地位于距两个市政井口约500英尺的地方,被住宅所包围。污染包括粘土层上方土壤中的多环芳烃(PAH)和挥发性有机烃(VOC)。被污染的土壤深度在地表以下2至20英尺(bgs)。补救措施包括开挖约26,000平方英尺(SF)的湿地和8,500 SF缓冲区的土壤。通过热脱附和异地处理土壤,并恢复湿地和缓冲区。作为监测自然衰减(MNA)计划的一部分,通过结合去除源区和自然衰减实现了地下水修复。站点关闭最大程度地降低了风险,并导致在当前条件下(对于住宅暴露场景)无重大风险。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号