STATUTORY APPROVAL PROCESS FOR CROSS-COUNTRY HYDROCARBON PIPELINE PROJECTS

机译:越野油气管道项目的法定批准程序

获取原文
获取原文并翻译 | 示例

摘要

Laying of petroleum and natural gas pipelines requires Clearances pertaining to Environment, Coastal Regulation Zone (CRZ), Forests and Wildlife from various statutory bodies of the Central and State Government depending on the proposed pipeline route. Because of the time-consuming appraisal process undertaken at various levels, planning the statutory approval process forms a very important part of the project implementation schedule. The project proponents have to forecast and plan well in advance for obtaining statutory approvals as scheduled. This paper details the clearances required for pipeline projects mainly from environmental angle, the procedures involved and difficulties faced by project proponents. It also suggests project proponents to plan the activities in advance and be updated on the new guidelines and notifications issued by the authorities. It also puts forth some recommendations to Statutory Authorities to simplify the procedures for speedy disposal of proposals related to pipeline projects.
机译:铺设石油和天然气管道需要中央和州政府各个法定机构根据拟议的管道路线进行有关环境,沿海管制区(CRZ),森林和野生动物的许可。由于在各个级别进行耗时的评估过程,因此计划法定批准过程是项目实施时间表中非常重要的一部分。项目支持者必须提前进行预测和计划,以便按计划获得法定批准。本文主要从环境角度,项目支持者所涉及的程序和面临的困难的角度详细说明了管道项目所需的间隙。它还建议项目支持者提前计划活动,并根据当局发布的新指南和通知进行更新。它还向法定机构提出了一些建议,以简化快速处理与管道项目有关的建议的程序。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号