An Integer Programming Model of Reinvestment Strategy Based Project Portfolio Selection and Scheduling with Constrained Resource

机译:资源约束下基于再投资策略的项目组合选择与调度的整数规划模型

获取原文
获取原文并翻译 | 示例

摘要

Selecting an appropriate series of projects among numerous candidates and assigning start and finish time for every selected project under the constraints of limited resource does matter in the project management. With the introduction of annual budget and time value of capital, the proposed problem becomes more complex. In this paper, an integer programming model is proposed and constructed to model the situation of selecting and scheduling suitable project portfolio at the same time with constrained resource, in which reinvestment strategy is also applied in the process. In reality, annual budget is time-dependent, so it is necessary to take time value of capital into account during the modeling process. The use of reinvestment strategy means that the profit earned by accomplished projects is put into the resource pool to finance more projects to be selected and executed in order to make the total profit of project portfolio maximal. During the modeling progress, others constraints are also considered, like project interrelationship, to represent closely practical situations.
机译:在有限的资源约束下,从众多候选人中选择适当的一系列项目,并为每个选定的项目分配开始和结束时间,这对项目管理至关重要。随着年度预算和资金时间价值的引入,提出的问题变得更加复杂。本文提出了一种整数规划模型,并在资源有限的情况下构造了该模型,以对同时选择和安排合适的项目组合的情况进行建模,并在此过程中采用了再投资策略。实际上,年度预算是时间相关的,因此在建模过程中必须考虑资本的时间价值。使用再投资策略意味着将已完成项目所获得的利润放入资源库中,以资助更多要选择和执行的项目,以使项目组合的总利润最大化。在建模过程中,还考虑了其​​他约束(例如项目相互关系)来表示实际情况。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号