Drilling Out into the Ocean – Lessons Learned from a Pilot Bore Geotechnical Exploration

机译:钻进海洋-从钻探岩土工程中汲取的教训

获取原文
获取原文并翻译 | 示例

摘要

Nalcor Energy is developing the Lower Churchill Project, involving hydroelectric generation and transmission fromrnLabrador to the island of Newfoundland. As part of this work, horizontal directional drilling (HDD) method will bernused to construct six (6) landfall crossings beneath the shorelines of the Strait of Belle Isle (SOBI) separatingrnLabrador and Newfoundland. Each HDD installation will consist of a 10.75-inch (273 mm) diameter steel casing tornhouse individual HVdc electrical cables (to be installed later in a second pass). The length of the steel casingrninstallations will range between 4,921 feet (1,500 metres) and 8,200 feet (2,500 metres). The termination depth ofrnthe HDD installations will range between 200 (60 metres) and 295 feet (90 metres) below sea level. The geologyrnconsists of ocean floor sediments, sedimentary sandstone, limestone, dolostone, shale and Precambrian granite. Thernocean floor sediments consist of clay, silt, sand, gravels, cobbles and boulders.rnAs part of an in-depth risk reduction measure, a HDD pilot bore geotechnical investigation was completed tornsupplement traditional shoreline-based geotechnical investigations. This pilot bore program also provided a meansrnto assess the applicability of using standard and non-standard guidance systems and drilling approaches from bothrnthe HDD industry as well as the oil and gas industry. In addition, it provided a means to verify contingency plansrndeveloped for the proposed HDD installations. This paper highlights the lessons learned from the 2011/2012 HDDrnpilot bore field program used to develop the ultimate SOBI landfall HDD design crossings.
机译:Nalcor Energy正在开发下丘吉尔项目,该项目涉及水力发电和从拉布拉多到纽芬兰岛的输电。作为这项工作的一部分,将采用水平定向钻探(HDD)方法来在Belle Isle海峡(SOBI)分离拉布拉多和纽芬兰的海岸线下方建造六(6)个登陆口。每个硬盘驱动器安装将包括直径为10.75英寸(273毫米)的钢制外壳,可撕开单独的HVdc电缆(稍后将在第二遍安装)。钢制外壳的安装长度为4,921英尺(1,500米)至8,200英尺(2,500米)。 HDD安装的终止深度将在海平面以下200(60米)至295英尺(90米)之间。地质学由海床沉积物,沉积砂岩,石灰岩,白云岩,页岩和前寒武纪花岗岩组成。 Thernocean底泥包括粘土,淤泥,沙子,砾石,鹅卵石和巨石。作为深度降低风险措施的一部分,HDD飞行员岩土工程研究已完成,以补充传统的基于海岸线的岩土工程研究。该试验钻孔程序还提供了一种方法,以评估使用HDD行业以及石油和天然气行业的标准和非标准导向系统以及钻井方法的适用性。此外,它还提供了一种方法,以验证为建议的HDD安装制定的应急计划。本文重点介绍了从2011/2012 HDDrnpilot钻孔现场程序中汲取的经验教训,该程序用于开发最终的SOBI登陆HDD设计通道。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号