Design and Rapid Construction of Phase III RCC Cofferdam of the Three Gorges Project

机译:三峡工程三期碾压混凝土围堰设计与快速施工

获取原文
获取原文并翻译 | 示例

摘要

The Phase III RCC cofferdam of the Three Gorges Project (TGP), with a max height of 115m, is a Class I temporary structure. On the first stage (phase I), the right shoulder of cofferdam under EL. 50m (58m) was constructed. On the second stage, RCC volume placeed was about 1. 1 million m3, which was finished within 4 months, with a max monthly placement intensity of 476, 000m3. The paper is mainly focused on the structural layout design of RCC cofferdam, rapid RCC placement schemes and measures.
机译:三峡工程(TGP)的​​三期RCC围堰,最大高度为115m,属于I类临时结构。在第一阶段(第一阶段),围堰的右肩在EL之下。建造50m(58m)。在第二阶段,放置的RCC量约为1。1百万立方米,在4个月内完成,最大每月放置强度为476,000m3。本文主要研究碾压混凝土围堰的结构布置设计,碾压混凝土快速布置方案和措施。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号