首页> 外文会议>Waste Management Symposium >DESIGNING AND CONSTRUCTING HANFORD'S WASTE TREATMENT PLANT - CHALLENGES AND PROGRESS IN THE NATION’S LARGEST CONSTRUCTION PROJECT
【24h】

DESIGNING AND CONSTRUCTING HANFORD'S WASTE TREATMENT PLANT - CHALLENGES AND PROGRESS IN THE NATION’S LARGEST CONSTRUCTION PROJECT

机译:汉福德废物处理厂的设计与构建 - 国家最大建设项目的挑战与进展

获取原文

摘要

There are many challenges in the design and construction of the Department of Energy’s (DOE’s) $5.7 billion Hanford Tank Waste Treatment and Immobilization Plant (WTP) that is rising above ground at the Hanford site. Being built to process radioactive waste from cold war plutonium production operations contained in 177 underground tanks, engineering is about 85% and construction is at about 45% complete. The project, comprised of 3 large process buildings - the Pretreatment (PT) facility, High Level Waste (HLW) facility, and Low Active Waste (LAW) facility, is scheduled to complete construction in 2008 and hot commissioning in early 2011. Design challenges have included staffing for and performing extensive design for a closecoupled design/construction project, completion of the process design with a large confirmatory testing program, and the successful employment of the “black cell” design approach involving operating spaces for which no entry in a process cell is presumed in 40 years of plant operation. Construction on the 57-acre site started with first concrete in July 2002. Ultimately some 250,000 cubic yards of concrete with 40,000 tons of rebar and 27,000 tons of embeds will be placed and 200 miles of mostly small-bore piping will be installed in the three facilities [1]. A key construction hurdle is installing the mazes of piping associated with the process vessels. Many vessels have 30 to 40 piping penetrations on the head, creating very congested areas for installation and inspection and the need to use advanced examination techniques. Other challenges specific in the PT facility include proving that the resin used in the crucial cesium ion exchange process will perform adequately, use of fluidic pulse jet mixers (PJMs) on high rheology non-Newtonian wastes, and the precision installation of remote jumpered equipment in the hot cell. In LAW, the fabrication and installation of the huge melters is a challenge, and in HLW the design and testing of the remotely operated and maintained melters is a key challenge.
机译:还有在设计许多挑战和能源的部建设(能源部)$ 5.7十亿汉福德罐废物处理和被地上升起在汉福德场地固定化厂(WTP)。正在兴建处理包含在177个地下油罐从冷战钚生产操作放射性废物,工程在85%左右,并建设约45%完成。该项目由3层大工艺建筑 - 预处理(PT)设备,高放废物(HLW)设施和低活性废料(LAW)设备,完成预定建设在2008年和2011年初的设计挑战热试车已经包括了工作人员,并进行了广泛的设计为closecoupled设计/建设项目,工艺设计与大量的验证测试程序,以及涉及用于其经营场所的“黑电池”设计方法的成功就业完成的过程中没有条目电池40年电厂运行的推测。在57英亩的土地上建设开始第一罐混凝土,2002年最终备有4万吨螺纹钢和27000吨嵌入功能的混凝土将被放置的一些250000立方码而且大多小口径管道200英里将被安装在三个七月设施[1]。重点建设的障碍是安装的管道与进程相关船只迷宫。许多船只对头部30〜40管贯穿,创造安装和检验,并使用先进的检测技术的需求非常拥挤的地区。其他挑战的具体在PT设施包括证明在关键的铯离子交换方法中使用的树脂,会充分进行,使用于高流变性非牛顿废物流体脉冲喷射混合器(PJMs)的,并且在远程跳接设备的精度安装热室。在法律上,巨大的熔炉的制造和安装是一个挑战,而在高放废物的设计和遥控操作和维护胶机测试是一个关键的挑战。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号