Design of Atlanta Raw Water Supply Program

机译:亚特兰大原料供应计划设计

获取原文

摘要

The City of Atlanta is converting an over-a-century-old quarry into a 2.4 billion-gallon raw water storage facility. The system consists of a deep hard rock tunnel, two deep pump stations, two dropshafts and multiple connecting adits and shafts. Bored with a TBM from tunnel portal at the quarry base, the tunnel is approximately 24,000ft long, 250ft to 450ft deep, 13ft in bore diameter, and is partially concrete lined with modified contact grouting to control water infiltration/exfiltration. CFD modeling is performed for the pressurized system. Various shaft construction techniques are used, including drill & blast, blind bore drilling and raisebore drilling.
机译:亚特兰大市正在将一个多世纪的历史上的采石场转化为24亿加仑的原料储存设施。该系统由深硬岩隧道,两个深泵站,两个下落轴和多个连接坯和轴组成。在采石场的隧道门户网站上厌倦了隧道,隧道大约24,000英尺长,250英尺深,孔径为13英尺,是衬砌的改良接触灌浆的部分混凝土,以控制水渗透/曝液。对加压系统执行CFD建模。使用各种轴施工技术,包括钻孔和爆破,盲孔钻孔和钻孔钻孔。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号