CONSTRUCTION OF THE POWERHOUSE CAVERN FOR THE PUMPED STORAGE SCHEME KOPS II IN AUSTRIA

机译:奥地利泵送存储方案KOPS II的泵浦洞穴建设

获取原文

摘要

In the period between November 2004 and December 2005 (13 months) a total volume of 125,000 m~3 was excavated in the power house and the transformer cavern. The excavation works for the tunnels and shafts-all in all 1,782 m-were performed in parallel to the excavation works for the caverns and amounted to a total of 78,000 m~3. The performance level attained with respect to the lining works is also quite remarkable, as is illustrated by the fact that in the period from December 2005 to May 2007 (1.5 years) 48,000 m~3 of concrete were installed in the cavern. The numerous lining and backfilling works in the tunnels, shafts and other auxiliary structures were carried out simultaneously with the concreting works in the cavern. This outstanding accomplishment was only made possible by an intense work preparation throughout the project implementation period and by the strong commitment of all specialists involved. At peak times, the number of skilled workers on site was in the range of approx. 130. All works were performed continuously in day and night shifts, only interrupted by the traditional Christmas and Easter holiday.
机译:在2004年11月至2005年12月(13个月)的期间(13个月)在动力屋和变压器洞穴中挖掘了125,000米〜3的总体积。隧道和轴的挖掘工程 - 全部在所有1,782米的挖掘中与挖掘机进行平行,以为洞穴工作,总计78,000 m〜3。关于衬里工程所获得的性能水平也是非常显着的,如2005年12月至2007年5月(1.5年)的事实所示,洞穴安装了48,000米〜3的混凝土。在隧道,轴和其他辅助结构中的许多衬里和回填工作在洞穴中的混凝土工作中同时进行。这一突出的成就仅在整个项目实施期间和所有所涉及的专家的强烈承诺中才有可能。在高峰时段,现场技术人员的数量在约量的范围内。 130.所有作品在白天和夜班中不断进行,只有传统的圣诞节和复活节假期中断。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号