The proposed 1.83km long twin bore A3 Hindhead road tunnel planned for construction in 2008 is being delivered under a Highways Agency Early Contractor Involvement (ECI) contract. The proposed construction methodology is progressive mechanical excavation of a horseshoe shaped tunnel with shotcrete installed close behind the face using robotic spraying equipment. The tunneling medium is a 'soft rock' sandstone for which there was little previous tunneling experience, requiring extensive geotechnical investigations and an innovative approach to lining design. A 240m long portal section though sandy material utilising a steel pipe umbrella is also required. This paper describes the development of the tunnel planning and design including the most recent developments in UK road tunnels, and the innovation included in the 'permanent' primary lining design.