Calculation and Analysis for the Time-Dependency of Settlement of the Single-Driven Pile in Double-Layered Soft Clay

机译:双层软粘土沉降时间依赖性的计算与分析

获取原文
获取外文期刊封面目录资料

摘要

The dissipation of the pile-side excess pore water pressure caused by pile driving is the main cause of the settlement of single-driven pile in soft clay. Based on the three-dimensional consolidation theory, the calculation formula for reconsolidation settlement of pile-side soil was derived. In addition, the calculation formula for the settlement of the single-driven pile caused by the pile-side soil reconsolidation settlement was derived using the pile-soil interaction principle and by combining boundary conditions in double-layered soft clay. An engineering example was also calculated and analyzed. The research shows that the settlement of the single-driven pile caused by the dissipation of pile-side excess pore water pressure is larger and is far more than that caused by the vertical load. Thus, the settlement of the driven pile was larger than that of the bored pile. The research also indicates that the settlement of the single-driven pile increases with time because of the influence of the pile-side soil reconsolidation, and then it gradually becomes stable.
机译:桩驾驶引起的桩侧过量孔隙水压的耗散是软粘土中单射桩沉降的主要原因。基于三维固结理论,衍生桩侧土壤重新垄断沉降的计算公式。此外,通过桩 - 土壤相互作用原理和通过将边界条件混合双层软粘土中的边界条件来得出由桩侧土壤重新覆膜沉降沉降的计算公式。还计算并分析了工程示例。该研究表明,由桩侧过量孔隙水压力耗散引起的单驱动桩的沉降更大,远远超过垂直载荷引起的。因此,从动桩的沉降大于钻孔桩的沉降。该研究还表明,由于桩侧土壤重新覆透的影响,单次桩的沉降随着时间的推移而增加,然后逐渐变得稳定。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号