North American Western System Outages of July 2nd and August lOth, 1996:Issues and Technical Solutions

机译:北美西部系统中断7月2日和8月Loth,1996年:问题和技术解决方案

获取原文

摘要

On July 2, 1996, a significant disturbance occurred on the Western Systems Coordinating Council (WSCC) interconnected transmission system. This outage was triggered when a flashover occurred between a 345 kV transmission line and a tree that had grown too close to the line. This line spans the 234 miks between the Jim Bridger generating plant near Rock Springs, Wyoming, and the Kinport substation in southeastern Idaho. A simultaneous loss of a parallel 345 kV line caused by a bad protective device contributed to the severity of the outage. Loss of these two lines initiated a protection program that shut down two generating units at the Jim Bridger plant. A number of events took place after this due to low voltages in Idaho and Oregon. This disturbance split the entire WSCC system into five islands and interrupted electric service to approximately 2 million customers. Service was restored to majority of customers within 30 minutes.
机译:1996年7月2日,西方系统协调委员会(WSCC)相互连接的传输系统发生了重大干扰。 当345 kV输电线路和一棵树之间发生太近线的树之间发生闪光灯时,将触发此停机。 这条线涵盖了吉姆桥梁在岩石泉,怀俄明州的发电厂之间的234米,以及位于爱达荷州东南部的吉姆明和Kinport变电站。 由不良保护装置引起的并联345 kV线的同时损失导致中断的严重程度。 这两条线的丢失发起了一个保护程序,在Jim Bridger工厂关闭了两个发电机。 由于爱达荷州和俄勒冈州的低电压,在此发生了许多事件。 这种干扰将整个WSCC系统分成五个岛屿并中断电力服务至约200万客户。 服务在30分钟内恢复到大多数客户。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号