Understanding Cost Growth During Operations of Planetary Missions: An Explanation of Changes

机译:在行星特派团运营期间了解成本增长:改变的解释

获取原文

摘要

In the development of project cost estimates for interplanetary missions, considerable focus is generally given to the development of cost estimates for the development of ground, flight, and launch systems, i.e., Phases B, C, and D. Depending on the project team, efforts expended to develop cost estimates for operations (Phase E) may be relatively less rigorous than that devoted to estimates for ground and flight systems development. Furthermore, the project team may be challenged to develop a solid estimate of operations cost in the early stages of mission development, e.g., Concept Study Report or Systems Requirement Review (CSR/SRR), Preliminary Design Review (PDR), as mission specific peculiarities that impact cost may not be well understood. In addition, a methodology generally used to develop Phase E cost is engineering build-up, also known as "grass roots". Phase E can include cost and schedule risks that are not anticipated at the time of the major milestone reviews prior to launch. If not incorporated into the engineering build-up cost method for Phase E, this may translate into an estimation of the complexity of operations and overall cost estimates that are not mature and at worse, insufficient. As a result, projects may find themselves with thin reserves during cruise and on-orbit operations or project overruns prior to the end of mission. This paper examines a set of interplanetary missions in an effort to better understand the reasons for cost and staffing growth in Phase E. The method used in the study is discussed as well as the major findings summarized as the Phase E Explanation of Change (EoC). Research for the study entailed the review of project materials, including Estimates at Completion (EAC) for Phase E and staffing profiles, major project milestone reviews, e.g., CSR, PDR, Critical Design Review (CDR), the interviewing of select project and mission management, and review of Phase E replan materials. From this work, a detailed picture is constructed of why cost grew during the operations phase, even to the level of specific events in the life of the missions. As a next step, the Phase E EoC results were gleaned and synthesized to produce leading indicators, i.e., what may be identifiable signs of cost and staffing growth that may be present as early as PDR or CDR. Both a qualitative and quantitative approach was used to determine leading indicators. These leading indicators will be reviewed and a practical method for their use will be discussed.
机译:在制定行星际任务的项目成本估计中,通常对地面,航班和发射系统开发的成本估算的发展,即阶段B,C和D的开发。根据项目团队,努力开发运营成本估算(e)的努力可能比拟拟给地面和飞行系统开发估计的规模相对不那么严谨。此外,项目团队可能受到挑战,以便在使命发展的早期阶段开发运营成本的稳定估计,例如概念研究报告或系统要求审查(CSR / SRR),初步设计审查(PDR),作为特定特定的特殊性影响成本可能无法康复。此外,一般用于开发e成本的方法是工程堆积,也称为“草根”。阶段E可以包括在发布前的主要里程碑审查时未预期的成本和计划风险。如果未结合到阶段E的工程建立成本方法中,这可以转化为对运营复杂性的估计和整体成本估算并不成熟并且更严重,不足。因此,项目可能在使命结束之前巡航和轨道运营或项目超支期间发现自己的储备。本文审查了一系列行星期际任务,以更好地了解E期成本和人员分配增长的原因。讨论了该研究中使用的方法以及作为变更阶段的e e解释(EoC)的主要调查结果。 。研究该研究需要审查项目材料,包括e e e和人员配置个人资料的完成(EAC),重大项目里程碑评论,例如CSR,PDR,关键设计评论(CDR),选择项目和使命的面试管理和审查e e e replan材料。根据这项工作,构建了一种详细的图片,为什么运营阶段成本增长,甚至到任务生命中的特定事件的水平。作为下一步,收集EoC结果,并合成以生产领先指标,即,可能是可能是可识别的成本和人员配备成长的迹象,这些迹象可能与PDR或CDR一起出席。定性和定量方法都用于确定领先指标。将讨论这些领先指标,并将讨论其使用方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号