Meeting the Challenges of Parallel HDD Construction: A Case Study for St. John's County, Florida

机译:迎接平行HDD建设的挑战:佛罗里达州圣约翰县的案例研究

获取原文

摘要

St. Johns County Utilities Department (SJCUD) sought to expand their reclaimed water distribution system to meet projected future reclaimed demands resulting from a new development within the St. Augustine Florida area and to comply with new goals to improve groundwater resources and reduce nutrient loading— that were developed for the Lower St. Johns River (LSJR) by the Florida Department of Environmental Protection (FDEP). CDM Smith was contracted to design and provide engineering services during construction for approximately 12,800 linear feet (lf) of reclaimed water main along International Golf Parkway (IGP). To realize potential cost savings and prepare for future service demands, approximately 7,800 lf of parallel force main was also added to the project during design. The project was selected by the St. Johns River Water Management District (SJRWMD) to receive cost-share funding equal to one-third of the estimated construction cost for alternative water supply development.
机译:圣约翰县公用事业部门(SJCUD)试图扩大其开垦的水分配系统,以满足由圣奥古斯丁佛罗里达地区的新发展的预计未来的再生要求,并遵守新的目标,以改善地下水资源,减少营养加载 - 由佛罗里达州的环境保护部(FDEP)为佛罗里达州的下部圣约翰河(LSJR)开发。 CDM史密斯在建设期间签约并提供工程服务,沿着国际高尔夫公路(IGP)的再生水主要的12,800英尺(LF)。为了实现潜在的成本节约和为未来的服务需求做好准备,在设计期间还将大约7,800升的平行力主要添加到项目中。该项目由St. Johns River Water Management District(SJRWMD)选出,以获得等于估计建筑成本的一三分之一的替代供水开发的费用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号