How many types of critical activities exist? A conjecture in need of proof

机译:存在多少种类型的关键活动?需要证明的猜想

获取原文

摘要

The Precedence Diagramming Method (PDM) is the prevalent scheduling technique used for temporal planning of projects. Critical paths require special attention during the course of planning as their lengths define the project duration. However, increasing/decreasing the duration of an activity on the critical path does not necessarily results in a longer/shorter project duration. Responses of the critical path in a PDM network for small changes of the duration of a critical activity can be classified into six categories, while nine different possible categories exist in theory. The modeling capabilities of PDM recently have been extended by the introduction of a) point-to-point relations, b) continuous relations, and c) non-linear activity (production-time) functions. The paper presents the following conjecture that needs a proof: The number of existing types of critical activities remains six when using the recently developed precedence relations and non-linear production-time functions for activities. The theory of the different types of critical activities is briefly discussed and the mathematical model of the generalized PDM technique is presented. An additional feature presented in the paper beyond defining the conjecture is the introduction of influence lines for project duration that have never been used in project management before. Influence lines can be of great help in understanding the nature of critical activities. Papers providing solutions or confuting this conjecture will be honored with the CCC 2017 award.
机译:优先介首图方法(PDM)是用于项目的时间计划的普遍调度技术。在规划过程中,关键路径需要特别注意,因为它们的长度定义了项目持续时间。然而,增加/减少关键路径上的活动的持续时间不一定导致更长/更短的项目持续时间。 PDM网络中临界路径对临界活动持续时间的小变化的响应可以分为六个类别,而九个不同可能的类别在理论上存在。 PDM的建模能力最近通过引入了一个)点对点关系,B)连续关系和C)非线性活动(生产时间)功能。本文介绍了需要证明的猜想:使用最近开发的优先关系和活动的非线性生产时间函数时,现有类型的关键活动的数量仍然是六个。简要讨论了不同类型的关键活动理论,并提出了广义PDM技术的数学模型。除了定义猜想之外,纸张中提出的附加功能是在项目管理之前从未用于项目持续时间的影响线。影响线在理解关键活动的性质方面可能具有很大的帮助。提供解决方案或禁用本猜想的论文将享受CCC 2017奖项。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号