In the light of the characteristics of the cable construction model under complicated working conditions, it is found that there is no engineering experience to calculate the traction force of the stay tube section and the arc high drop section. This paper establishes the corresponding engineering mechanics models according to the construction site environment, which determines the engineering calculation formulas by theoretical deduction and the on-site industrial test verification, thus realizing the safe, economical and efficient laying of high-voltage cables under complex working conditions. Finally, the 220kV East Traction Station project is taken as an example to verify the proposed construction scheme. The results show that the laying and bending tasks can be successfully completed and all the indicators are in perfect conformity with the technical specifications.
机译:鉴于在复杂的工作条件下电缆施工模型的特性,发现没有工程经验来计算停留管部分的牵引力和弧形高落叶部分。本文建立了根据施工现场环境的相应工程力学模型,由理论扣除和现场工业试验验证决定了工程计算公式,从而实现了复杂的工作下的高压电缆安全,经济高效地铺设状况。最后,将220kV东牵引站项目作为示例来验证所提出的施工方案。结果表明,铺设和弯曲任务可以成功完成,所有指标都与技术规范完美符合。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号