Near Field Developments with an Upgraded Brown-Field Platform Rig: Sharing the Learning from a Three-Well Extended Reach Drilling (ERD) Program

机译:升级的棕色野外平台钻机附近的现场开发:从三大扩展到达钻井(ERD)计划中分享学习

获取原文
获取外文期刊封面目录资料

摘要

This paper will summarize the concept selection, concept definition, and modifications for a two-stage upgrade of a 35-yr old platform rig on a production platform to extend the drilling radius from 15 to 25 kft (Cutt 2007), the maximum working pressure (MWP) from 5 to 10 ksi, and how combined projects enabled the development of new fields which could not support subsea infrastructure. The paper will highlight the lessons learned at each stage of the upgrade and the drilling programs, focusing on how the legacy limitations of the original rig design and inherited constraints of 200% well slot utilization were mitigated to enable the drilling of a next generation of wells. The upgrade of the rig in two separate projects allowed the lessons learned from the first extended reach drilling (ERD) upgrade (Cutt 2007) to be applied to the second 10-ksi upgrade. This approach also allowed different approaches to be taken to achieve improved results. The drilling of redrilled wells on an old platform through depleted reservoirs constrained many aspects of well design; most specifically, casing sizes and maximum mud weights through intervals of reactive shale and depleted sands (Bennett et al, 1998). The company has global experience in new field developments with world class ERD wells (Elks et al, 2002; Walker 2008; Armstrong et al, 2011; McDermott et al, 2005; Viktorin et al, 2006; Elsborg et al, 2005; Woodfine et al, 2011) and the different approaches for new wells and redrilled wells will be compared. The paper will show how the challenges of ERD operations to 25 kft in a 6-in. hole size were overcome and will comprehensively address how some risk mitigations introduced new risks, with specific emphasis on managing an operation where the extreme requirements did not allow any fallback contingencies in the event of a problem.
机译:本文将总结一个概念选择,概念定义和修改在生产平台上的35年旧平台钻机的两级升级,以将钻孔半径从15到25 kft(Cutt 2007)扩展,最大工作压力(MWP)从5到10 KSI,以及组合项目如何启用无法支持海底基础设施的新字段。本文将突出显示升级和钻井计划的每个阶段的经验教训,重点是原始钻机设计的遗产限制和200%井间隙利用的继承的限制,以使下一代井的钻井能够钻探下一代井。两个单独的项目中的钻机升级允许从第一个扩展到达钻井(ERD)升级(CUTT 2007)中学到的经验教训,以应用于第二个10-KSI升级。这种方法还允许采取不同的方法来实现改进的结果。通过耗尽水库钻探旧平台上的红井钻孔约束了井设计的许多方面;最具体地,通过反应物流和耗尽砂的间隔(Bennett等,1998),套件尺寸和最大泥浆重量。公司拥有全球新型现场发展经验,与世界级ERD Wells(Elks等,2002; Walker 2008; Armstrong等,2011; McDermott等,2005; Viktorin等,2006; Elsborg等,2005; Woodfine Et将比较新井和红井井的不同方法。本文将展示ERD操作在6英寸中的25 kft挑战。克服孔尺寸并将全面解决一些风险减轻如何引入新风险,具体强调管理极端要求在发生问题时不允许任何后退违规行为。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号