Contrast Study on Prediction Models of the Post-construction Settlement of Embankment in Saline Soil Area

机译:盐水土壤堤防后施工沉降预测模型的对比研究

获取原文

摘要

Post-construction settlement is one of the main issues in high grade railway construction in saline areas. The efective solution to the problem is to find the post-construction settlement law for the guidance to the design and construction based on the field monitored data. After analyzing the large quantities of monitored data from the second double line of Lanzhou-Xinjiang Railway in saline areas, a new model is put forward. The standard hyperbolic model, the modified hyperbolic model and exponential model were applied to the forecasting settlements based on the same monitored data to test the presented new model. By comparing fitting, forecasting accuracy and stability of different methods, show that the new model has a high prediction accuracy and good stability, and the forecasting data agree well with the monitored data. The new model presents a new method for analysis and prediction of settlement, and it is found to be a good reference to post-construction settlement of embankment in saline areas.
机译:后建设结算是盐水区高级铁路建设中的主要问题之一。对问题的相关解决方案是基于现场监测数据找到对设计和施工的指导的建设后结算法。在盐水区兰州 - 新疆铁路的第二次双线分析大量监测数据后,提出了一种新模型。标准的双曲模型,改进的双曲模型和指数模型应用于基于相同的监视数据的预测结算,以测试所呈现的新模型。通过比较不同方法的拟合,预测精度和稳定性,表明新模型具有很高的预测精度和良好的稳定性,并且预测数据与受监控数据相吻合。该新模式提出了一种新的分析和预测解决方法,并发现它是对盐水区堤防后施工结算的良好介绍。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号